Project Information
City Council Report Executive Summary
In 1993 the residents of Carrollton approved a bond program that included
erosion control improvements for Highlands Creek between Marsh Lane
and Kelly Boulevard. A consultant was hired and the project proceeded
into design. After efforts to obtain eants failed, that project
was ceased.
Freese and Nichols was hired in May of 2000 to complete the preliminary
design for the
Highlands Creek Drainage Improvement project. The project included
hydrologic and hydraulic
analysis as well as an extensive public involvement plan. Out of
the f-nine residences located
on the creek, fifty-four of them were represented in the public
involnt process through their
participation in public meetings and/or response to mailers.
Through the process, the team developed a design which produced
support from 73% (43) of
the residents. Seven percent (4) have voiced their opposition, while
the remaining 20% (12)
have not commented on the proposed design. Appendix A contains a
phic illustration of the
residents’ opinions about the project.
The project is now at a point where further direction from City
Col is required. Following
are three options for this project as outlined in this report:
- Proceed into design and complete the entire project obtaining
all necessary easements.
- No action, leave creek as is and reallocate bond funds to other
drainage projects.
- Use a segmental approach to complete the improvements in areas
where homeowners are in support of the project.
With option one and option three, the public involvement process
sh continue with an effort
to gain approval from more homeowners. Field staking the limits
he project on the ground
will further illustrate to homeowners the impact or lack of impact
toir property. The details
of some homeowner’s concerns can then be worked out in final
design.
The segmental approach presents some potential future problems
fhe City. For example, as
the properties change ownership, residents may come to the City
as for improvements. Also,
residents who are left out of the project will most likely continue
toerience soil erosion and
tree loss. These issues may continue to cause the City staff and
Col problems well into the
future.
If the City Council wishes to proceed with final design of the
entproject, a commitment on behalf of the City to obtain all easements
necessary to construct theject through purchase or acquisition is
required.
Download
the complete report as an Adobe Acrobat file (3.5 mb PDF)
|